The Commercial Court has rejected an application to quash planning permission for Apple’s new multi-million Euro data centre in Athenry.

The €850m investment has been held up for years while a similar project in Denmark – originally announced alongside the Galway plans – is now close to completion.

The Danish centre will be up and running by the end of the year.

Apple has also announced plans to build a second data centre there, leading to fears it could shelve its Irish project.

One of the biggest capital investment projects earmarked for the west of Ireland, the centre is expected to create 300 construction jobs and 150 permanent on-site jobs.

Planning permission

Apple was given the go-ahead to proceed with the development by Galway County Council in February 2015.

That decision was re-affirmed by An Bord Pleanála in August 2016 – however the project has been delayed by a judicial review undertaken by three objectors to the project.

This morning Mr Justice Paul McDermott rejected that application – but put the case back for a week to allow them to respond.

Noel Doherty from the campaign group ‘Apple for Athenry’ travelled to Dublin to hear today’s judgement in person:

“Today’s decision has been a great decision for Athenry and the whole west of Ireland,” he said.

“I hope now that our public representatives will help us to develop the west coast of Ireland and to bring companies like Apple in to Athenry - and make Athenry a hub town for the whole of the west coast.

Environmental impact assessment

Two of the objectors, Sinéad Fitzpatrick and Allan Daly, claimed planning bosses failed to carry out a proper environmental impact assessment.

In his decision Mr Justice McDermott said An Bord Pleanála had undertaken an assessment that “encompassed consideration of the relevant cumulative effects both direct and indirect of the proposed development.”

He said its decision in this regard was “unimpeachable.”

The saga could yet run on for many more months, as the challengers retain the option to appeal the decision.

The Taoiseach has previously insisted that Apple remains committed to the project – pending planning approval.


Share this article


Read more about

News

Most Popular

Live: Title

Now playing

00:00:00 / 00:00:00
Added to queue
Removed from queue

On Air

Share

Share


Up next

Episode title
Show
Duration

You currently have no podcasts in your queue.

Go to podcasts

On Air

DOWN TO BUSINESS

DOWN TO BUSINESS

10:00-12:00

Share

Up next

FUTUREPROOF

FUTUREPROOF

12:00-13:00

Share

OFF THE BALL

OFF THE BALL

13:00-18:00

Share

THE PICTURE SHOW

THE PICTURE SHOW

18:00-19:00

Share

TED RADIO HOUR

TED RADIO HOUR

19:00-20:00

Share

The Peter Casey Report

The Peter Casey Report

20:00-21:00

Share

DOCUMENTARY AND DRAMA ON NEWST...

DOCUMENTARY AND DRAMA ON NEWSTALK

21:00-22:00

Share

YOU COULDN'T MAKE IT UP.

YOU COULDN'T MAKE IT UP.

22:00-22:30

Share

THE HARD SHOULDER

THE HARD SHOULDER

22:30-23:30

Share

FUTUREPROOF

FUTUREPROOF

23:30-00:00

Share

FUTUREPROOF

FUTUREPROOF

00:00-00:15

Share

BEST OF NEWSTALK

BEST OF NEWSTALK

00:15-07:00

Share

DOCUMENTARY AND DRAMA ON NEWST...

DOCUMENTARY AND DRAMA ON NEWSTALK

07:00-08:00

Share

BETWEEN THE LINES

BETWEEN THE LINES

08:00-09:00

Share

BOBBY'S LATE BREAKFAST

BOBBY'S LATE BREAKFAST

09:00-11:00

Share

ON THE RECORD

ON THE RECORD

11:00-13:00

Share

00:00:00 / 00:00:00

Share on